Plans to repair the Earl Reservoir dam took a step forward after the Woodbury Town Board cleared the project's environmental review.

At its November 5 meeting, the board determined that the planned repairs would not have a significant environmental impact, allowing the project to move ahead without a more detailed environmental study.

The project at 1 Coach Wilson Trail in Highland Mills includes repairs to the dam's concrete structure, spillway, outlet, valves and access walkway.

The reservoir's water level will be partially lowered so crews can reach the outlet. Town officials said this will be coordinated with the reservoir's regular seasonal lowering, with no change to the normal drawdown process expected.

The review also identified possible protected wildlife in the area, including timber rattlesnakes and northern long-eared bats. The work will have to follow the required protections for those species.

The town hopes to use an existing FEMA grant to pay for the work. Permits from the state Department of Environmental Conservation are still required, and no construction start date has been announced.


Quickway Road Between Rimenev Court and Van Buren Drive to Close for Two Weeks During Working Hours
  • Nov 21 2026
  • |
  • 5:53 PM

Americare Opens Rockland Location, Launches New Division Serving the Heimishe Community
  • Nov 21 2026
  • |
  • 5:49 PM